RENOVATION FLOOR PLAN & REFLECTED CEILING PLAN

 

FATHER JUDGE HIGH SCHOOL BIOLOGY LAB

In collaboration with McGillin Architecture

Project Team:
- Howard V. Lebold, AIA, LEED AP
- Dominic Martino

January 2025-April 2025

Program:
Classroom, Laboratory

Location:
3301 Solly Ave., Philadelphia, PA

Construction Area:
2,835 SF

Software:
AutoCAD

Responsibilities:
- Existing condition drawings
- Design
- Construction documentation
- Consultant coordination
- Product research

 

This project involved the partial renovation of a biology lab classroom suite for Father Judge High School, originally built in the 1950s. The scope included the demolition of existing partitions, the installation of a new storefront, and the replacement of existing doors, skylights, furniture, casework, lighting fixtures, plumbing fixtures, and mechanical equipment.

 
 
 